City of Maple Grove
App. Status: Closed
Valid: 01/16/2017 - 06/30/2018City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369
Kelly Matzke (612-968-3615)
APPLICANT
Applicant: |
|
PROJECT
Nature of Work: | Service Installation |
Surface to be disturbed: | Boulevard |
Work to start on or after: | 01/16/2017 |
To be completed on or before: | 06/30/2018 |
Applicant Project No.: | CP80594407 |
INSTALLATION / CONSTRUCTION
Attach detailed plan sheet: |
|
Size and kind of pipe: | 1/2" Plastic MGC# 15-5586 |
Depth from surface: | 36"- 48" |
Length of utility construction: | 0 |
Method of installation: | Open Trench |
Machine excavation: | Yes |
Development: | New |
LOCATION
Location/Address: | 11399 82ND PL N - MGC# 16-5586 |
Mark the installation/construction location on the map: |
|
Mark the location of the installation How to use: 1. Use only one option (dot, line, or polygon) 2. Made a mistake? Click on feature and press delete key. |
|
Will traffic detouring be necessary? | No |
Terms
Contact the Right-of-Way Technician by phone (612-968-3615) 24 hours prior to starting work, and upon completion so a final inspection can be completed in a timely manner.
You must adhere to [url=https://www.revisor.mn.gov/statutes/?id=216D]Minnesota Statutes 2015 CHAPTER 216D. EXCAVATION NOTICE SYSTEM[/url]
Notify all affected properties in writing prior to beginning work.
All cabinets, boxes, pedestals, etc. at corners must meet the City of Maple Grove's City Code, Sec. 360818 traffic visibility at corner lots.
All large trucks or large equipment are not allowed on any boulevard sidewalk or bituminous trails unless prior approval has been granted by the Right-of-Technician.
All signing for equipment in street must conform to the current MnDOT Manual on Uniform Traffic Control Devices.
Pneuma gophering is not allowed by the City of Maple Grove in this area.
All underground utilities must be placed a minimum of 36" and 48" maximum below finished top of curb elevation.
No hand holes or pot-holing in bituminous trails unless approved by the Right-of-Way Technician.
All disturbed areas must be returned to their original conditions within 30 days.
Lawn / Blvd areas must be restored per 28-105 of the Maple Grove Code of Ordinances.
Must adhere to MnDOT's Standard Specifications for Construction, Section 2575 and Maple Grove's specification for grading, landscaping and traffic control.
Notify Right-of Way Technician when work under this permit is completed, not at year's end.
Flag or mark utility location as required by state statue prior to calling in locates.
No work shall begin this year if it cannot be properly restored this year (unless emergency).
Street crossings to be installed perpendicular to street whenever possible.
Invoice #324 (12/28/2016)
Charge | Cost | Quantity | Total |
---|---|---|---|
Grand Total | |||
Total | $0.00 | ||
Due | $0.00 |
Approvals
Approval | Signature | Options |
---|---|---|
Applicant | Jody Cox - 12/28/2016 1:25 PM 578f7c41f6eb9c378f77f138985ee89e ccc06dc58b65207b8dfbc3372da543f0 | |
#1 Approved By | Kelly Matzke - 01/06/2017 11:09 AM bc6fc0dd99137e1e78423b0efb3a2354 352d351dfc3acc29ab2e9c8d9484ddd7 |
Text: | |
File(s): |
Text: | |
File(s): |