Excavation Permit Utility Installation Permit No. 2016-071, UID # 74
App. Status: Closed
Valid: 06/01/2016 - 10/01/2016
City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369

Kelly Matzke (612-968-3615)
 

APPLICANT

Applicant:
Name:
Alex Jon Carlson
Company:
Xcel Energy
Company Phone:Local Phone:
(651229 - 2512
(218591 - 5050
Email Address:
alex.j.carlson@xcelenergy.com
Mailing Address:
825 Rice St
St. Paul MN 55117

PROJECT

Nature of Work:
Other
Surface to be disturbed:
Gravel
Bituminous
Boulevard
Work to start on or after: 06/01/2016
To be completed on or before: 10/01/2016
Applicant Project No.: 12388331

INSTALLATION / CONSTRUCTION

Attach detailed plan sheet:
Size and kind of pipe:
#2 AL and 1/0 AL 
Depth from surface: 36"- 48"
Length of utility construction: 7000
Method of installation:
Directional Bore
Machine excavation: No
Development: Existing

LOCATION

Location/Address: 13366 85th PL
Mark the installation/construction
location on the map:
Mark the location of the installation
How to use:
1. Use only one option (dot, line, or polygon)
2. Made a mistake? Click on feature and press delete key.
Will traffic detouring be necessary? No

Terms

Requirements
  • Contact the Right-of-Way Technician by phone (612-968-3615) 24 hours prior to starting work, and upon completion so a final inspection can be completed in a timely manner.

  • You must adhere to [url=https://www.revisor.mn.gov/statutes/?id=216D]Minnesota Statutes 2015 CHAPTER 216D. EXCAVATION NOTICE SYSTEM[/url]

  • Notify all affected properties in writing prior to beginning work.

  • All cabinets, boxes, pedestals, etc. at corners must meet the City of Maple Grove's City Code, Sec. 360818 traffic visibility at corner lots.

  • All large trucks or large equipment are not allowed on any boulevard sidewalk or bituminous trails unless prior approval has been granted by the Right-of-Technician.

  • All signing for equipment in street must conform to the current MnDOT Manual on Uniform Traffic Control Devices.

  • Pneuma gophering is not allowed by the City of Maple Grove in this area.

  • All underground utilities must be placed a minimum of 36" and 48" maximum below finished top of curb elevation.

  • No hand holes or pot-holing in bituminous trails unless approved by the Right-of-Way Technician.

  • All disturbed areas must be returned to their original conditions within 30 days.

  • Lawn / Blvd areas must be restored per 28-105 of the Maple Grove Code of Ordinances.

  • Must adhere to MnDOT's Standard Specifications for Construction, Section 2575 and Maple Grove's specification for grading, landscaping and traffic control.

  • Notify Right-of Way Technician when work under this permit is completed, not at year's end.

  • Flag or mark utility location as required by state statue prior to calling in locates.

  • No work shall begin this year if it cannot be properly restored this year (unless emergency).

  • Street crossings to be installed perpendicular to street whenever possible.

Invoice #67 (05/26/2016)

Charge Cost Quantity Total
Non-Taxable
added 05/26/2016 2:45 PM

Excavation permit fee per occurance

$130.00 x 1 $130.00
added 05/26/2016 2:45 PM

In addition to excavation permit fee (per lineal foot)

$0.40 x 7,000 $2,800.00
Grand Total
Total $2,930.00
Payment 05/26/2016$2,930.00
Due$0.00
Action: Print  

Approvals

ApprovalSignatureOptions
ApplicantAlex J. Carlson - 05/26/2016 2:46 PM
cab46f1e605652a05c71ac350b11ed71
52393335ae986c5cec95ca0d34e64422
 
#1 Approved ByKelly Matzke - 06/07/2016 7:43 AM
e979b6784953f9105b3e152c2f4d31f4
f7597eb60a055625ae80a2d3da0e6340
 
Application has been approved. All signatures have been obtained.
Text: