City of Maple Grove
Excavation Permit Utility Installation Permit No. 2024-EP354, UID # 7325
App. Status: ApprovedCity of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369
Kelly Matzke (612-968-3615)
App. Status: ApprovedCity of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369
Kelly Matzke (612-968-3615)
APPLICANT
Applicant: |
|
||||||||||||||||||||||||||||||||||||||||
Additional email address to notify: | monica.braun@trustcompass.com |
CONTRACTOR
Contractor: |
|
PROJECT
Nature of Work: | Main Installation Service Installation |
Surface to be disturbed: | Bituminous* |
Work to start on or after: | 04/01/2025 |
To be completed on or before: | 07/31/2025 |
Applicant Project No.: | 118001 |
INSTALLATION / CONSTRUCTION
Provide a detailed work description: | Construction of fiber optic cable via directional bore |
Attach detailed plan sheet: | |
Size and kind of pipe: | (2) 1.25" HDPE |
Depth from surface: | 36"- 48" |
If other is selected, please provide additional information: | 60" Under Road Beds |
Length of utility construction in feet: | 3427 |
Method of installation: Note: Beginning July 1, 2025, all installations of underground telecommunications infrastructure must be performed by safety-qualified underground telecommunications installers that meet requirements per MN State Statute 326B.198. |
Directional Bore Other |
If other is selected, please provide additional information: | possible pot holing |
Development: | New |
Attach letter/door hanger used to notify property owners affected by construction: |
LOCATION
Location/Address: | 6125 Maple Grove Parkway Plymouth, MN |
Mark the location of the installation How to use: 1. Use only one option (dot, line, or polygon) 2. Made a mistake? Click on feature and press delete key. |
TRAFFIC CONTROL
Proposed work that impacts vehicle and/or pedestrian traffic will require a traffic control plan. Will traffic control be necessary? | Yes |
TRAFFIC CONTROL PLAN
Attach Traffic Control Plan: |
Invoice #6828 (09/23/2024)
Charge | Cost | Quantity | Total |
---|---|---|---|
added 09/23/2024 12:42 PM Excavation permit fee per occurance |
$160.00 | x 1 | $160.00 |
added 09/23/2024 12:42 PM In addition to excavation permit fee (per lineal foot) |
$0.20 | x 3,327 | $665.40 |
Grand Total | |||
Total | $825.40 | ||
Payment 09/23/2024 | $825.40 | ||
Due | $0.00 |
SPECIAL PROVISIONS
It is understood that the work and/or staging area along Maple Grove Parkway will not encroach into the vehicular travel lane. If it does, the applicant must resubmit a revised traffic control plan for review and approval.
It is also understood that the proposed pedestrian flagger control will minimize delays to pedestrians while safely traveling through the work area, and crossing the side streets.
Approvals
Approval | Signature |
---|---|
Applicant | Brett Christiansen - 10/18/2024 1:15 PM e35880cd97c1f3b24221879d0a1ed618 4dab18ca2f377c1fa0776b53905f6058 |
#1 Right of Way Technician Approval | Kelly Matzke - 10/21/2024 1:48 PM bf361196867434112bedb117a670f3ee d844f1e5553881304c2983bd0755f7c9 |
#2 Traffic Operations Engineer Approval | John Hagen - 10/21/2024 1:48 PM ff17bb76aa39606939627ab84448ad9b a4e688307121350b787021f18248dcaf |
Application has been approved. All signatures have been obtained.
Public Notes
Text: | |
File(s): |
Internal Notes
Text: | |
File(s): |