Excavation Permit Utility Installation Permit No. 2021-EP123, UID # 4601
App. Status: Approved
City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369

Kelly Matzke (612-968-3615)
 

APPLICANT

Applicant:
Name:
Bill Byers
Company:
Embarq Minnesota Inc dba CenturyLink QC
Company Phone:Local Phone:
(612431 - 3527
(651431 - 3527
Email Address:
bill.byers@lumen.com
Mailing Address:
425 MONROE STREET
ANOKA MN 55303
Additional email address to notify: becky.richter@centurylink.com

CONTRACTOR

Contractor:
Name:
Mike Gillette
Company:
Telcom Construction
Company Phone:Local Phone:
(612968 - 4959
(612968 - 4959
Email Address:
office@telcomconstruction.com
Mailing Address:
2218 200th St E
Clearwater MN 55320

PROJECT

Nature of Work:
Other
Surface to be disturbed:
Boulevard
Work to start on or after: 04/01/2021
To be completed on or before: 08/06/2021
Applicant Project No.: N.871245

INSTALLATION / CONSTRUCTION

Provide a detailed work description:
Relocate pedestal, remove pole and place new 6 pair buried service wire on City Project 19-08 Territorial Road.
Remove pole sta 26+20
Move Ped sta 26+20
Bore service wire acroos stree, 60"
Attach detailed plan sheet:
Size and kind of pipe:
6 pair service wire
Depth from surface: Other, I will describe below
If other is selected, please provide additional information: 60" at road crossing
Length of utility construction: 60
Method of installation:
Directional Bore
Hand Dig
Development: Existing

LOCATION

Location/Address: 13693 Territorial Road
Mark the location of the installation
How to use:
1. Use only one option (dot, line, or polygon)
2. Made a mistake? Click on feature and press delete key.

TRAFFIC CONTROL

Will traffic control be necessary? No

Terms

ACTIVATION REQUIRED
  • Contact Kelly Matzke at (612) 968-3615 at least 24 hours prior to construction to activate permit. Failure to contact Mr. Matzke to activate permit prior to work being started shall be considered a violation of the permit and grounds for dismissing contractor from the job site.

GENERAL
  • Article IV. Public Right-of-Way Management Ordinance will be enforced for work being done in the right-of-way.

  • All excavations taking place in right-of-way must conform to Minnesota Statute Chapter 216D. Excavation Notice System.

  • All rules and regulations for locates must conform to the most current Gopher State One Handbook.

  • Excavations taking place in the Maple Grove city limits in the Hennepin County right-of-way requires permits from the City of Maple Grove and Hennepin County.

  • Flagging or painting of route required by City of Maple Grove prior to calling in Gopher State One Call ticket.

  • All properties affected by excavation and construction must be notified in writing prior to beginning work.

  • The permit issued does not in any way imply an easement on private property or grant a right to encroach on private property.

  • A City of Maple Grove Excavation Permit shall be on site at all times and available upon request by any City official.

  • Safety vests must be worn by all people occupying the right-of-way.

CONSTRUCTION
  • All underground utilities must be placed a minimum of 36" and 48" maximum below finished top of curb elevation.

  • Any placement of utilities, including but not limited to cabinets, boxes, and pedestals must conform to City Code.

  • New ground structures must be placed near existing structures at a minimum of at least five feet away from hydrants.

  • Absolutely no removal of bituminous or concrete is allowed without prior approval from the City of Maple Grove.

  • Core drilling is not allowed in street, sidewalk, or trail without prior approval from City of Maple Grove. The City of Maple Grove does not allow core drilling to take place in ped ramps.

  • Vehicles, equipment, and materials are not allowed on sidewalks, trails, or ped ramps at any time unless the contractor performing work has exhausted all other alternatives, including, but not limited to lane closures, boulevard parking, etc. If it has been determined that all alternatives have been exhausted, permission must be obtained from City representative before proceeding to use sidewalks, trails, or ped ramps.

  • Any changes or revisions to the Excavation Permit after approval must be resubmitted and approved before proceeding with work in the right-of-way.

  • Street crossings must be installed perpendicular to the road to avoid future potholing in street.

  • Plowing and pneuma gophering are not acceptable forms of excavation allowed in the City of Maple Grove.

  • All open trenches and holes must be backfilled before leaving work site at the end of the day.

  • All flags from locates must be removed and picked up immediately once excavation has been completed.

  • Inclement weather shall be reason for delay of the project start or suspension of the project as determined by the City of Maple Grove.

TRAFFIC CONTROL
  • All permit applications requiring traffic control shall conform to the most recent version of the Minnesota Manual on Uniform Traffic Control Devices, including the Temporary Traffic Control Zone Layouts Field Manual, and be approved by the Transporation Operations Engineer.

  • The City of Maple Grove only allows traffic control to occur during off peak hours, which is between 9:00am-3:00 pm Monday thru Friday.

  • All traffic control devices must be removed from the job site promptly upon completion of work.

  • Traffic control on weekends requires prior approval from Transportation Operations Engineer John Hagen. John can be reached via email at jhagen@maplegrovemn.gov or 763-494-6364.

RESTORATION
  • Restoration must conform to Section 28-105. Restoration of Right-of-Way.

  • Restoration Requirements on Soft Surfaces:

    1. Turf: Hydroseeding is required unless otherwise directed by Right-of-Way Technician.
    2. Soil: Six inches of topsoil is required on all boulevards that are damaged.
    3. Sprinklers: Restore to prior condition with like materials and equipment.
    4. Pet Fences: Check for continuity after repair.
    5. Landscaping: Restore to original with like materials.
  • Removal/Restoration Requirements on Hard Surfaces:

    1. Bituminous: Shall be removed and restored in a timely matter to its original or better condition.
    2. Concrete: Shall be removed and restored in a timely matter to its original or better condition.
    3. Driveways: Notify Right-of-Way Technician of any damage and address with homeowner.
  • Restoration Requirements in areas where core drills were approved:

    1. Bituminous: Core drills in bituminous paths are replaced at width of path (example: 8 foot wide path is replaced 8'x8' per core).
    2. Concrete: Core drills in sidewalks require a minimum of two panels to be replaced per core to assure base has been properly reestablished.
  • All disturbed areas during excavation must be restored to their original condition within 30 days.

  • Damage on boulevards due to vehicles and equipment must be restored and treated the same way that excavation damage is restored.

  • Work completed in winter months must notify City with plans for restoration to take place in the spring.

  • Once restoration has been completed, contact Kelly Matzke at (612) 968-3615 or change status on permit software so an inspection can be completed in a timely manner. Failure to notify the City will result in all permits with the City of Maple Grove being put on hold until notification takes place.

ADDITIONAL INFORMATION
  • All contractors, including subcontractors, must be registered with the City of Maple Grove to do work in the right-of-way. Contractors doing work in the right-of-way that are not registered with the City will be considered in violation, and will be dismissed from the work site until registration is completed.

  • Absolutely no removal of bituminous or concrete is allowed during winter months.

Invoice #4082 (05/20/2021)

Charge Cost Quantity Total
Grand Total
Total $0.00
Due$0.00
Action: Print  

Approvals

ApprovalSignatureOptions
ApplicantBecky Richter - 05/20/2021 2:33 PM
802dd425f5dca61c31b2dfb5815954da
03bb89b8cc1e1843bb6f2b49acd5cc8b
 
#1 Right of Way Technician ApprovalKelly Matzke - 05/25/2021 7:41 AM
3c5944f32162a1fc2cd11be9496cb5c1
db2718aa64af2d5023214e1fc64ce9bd
 
Application has been approved. All signatures have been obtained.