Excavation Permit Utility Installation Permit No. 2016-253, UID # 435
App. Status: Closed
Valid: 12/27/2016 - 05/31/2017
City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369

Kelly Matzke (612-968-3615)
 

APPLICANT

Applicant:
Name:
Jason Darrington
Company:
Xcel Energy
Company Phone:Local Phone:
(763493 - 1649
(763493 - 1649
Email Address:
jason.darrington@xcelenergy.com
Mailing Address:
8701 Monticello Lane
Maple Grove mn 55369

PROJECT

Nature of Work:
Other
Surface to be disturbed:
Boulevard
Work to start on or after: 12/27/2016
To be completed on or before: 05/31/2017
Applicant Project No.: 12472043

INSTALLATION / CONSTRUCTION

Attach detailed plan sheet:
Size and kind of pipe:
N/A
Depth from surface: Other, I will describe below
If other is selected, please provide additional information: Removal
Length of utility construction: 0
Method of installation:
Other
If other is selected, please provide additional information:
Removal of pole line along Hemlock Lane N
Machine excavation: No
Development: Existing

LOCATION

Location/Address: 11701 Central Park way
Mark the installation/construction
location on the map:
Mark the location of the installation
How to use:
1. Use only one option (dot, line, or polygon)
2. Made a mistake? Click on feature and press delete key.
Will traffic detouring be necessary? No

Terms

Requirements
  • Contact the Right-of-Way Technician by phone (612-968-3615) 24 hours prior to starting work, and upon completion so a final inspection can be completed in a timely manner.

  • You must adhere to [url=https://www.revisor.mn.gov/statutes/?id=216D]Minnesota Statutes 2015 CHAPTER 216D. EXCAVATION NOTICE SYSTEM[/url]

  • Notify all affected properties in writing prior to beginning work.

  • All cabinets, boxes, pedestals, etc. at corners must meet the City of Maple Grove's City Code, Sec. 360818 traffic visibility at corner lots.

  • All large trucks or large equipment are not allowed on any boulevard sidewalk or bituminous trails unless prior approval has been granted by the Right-of-Technician.

  • All signing for equipment in street must conform to the current MnDOT Manual on Uniform Traffic Control Devices.

  • Pneuma gophering is not allowed by the City of Maple Grove in this area.

  • All underground utilities must be placed a minimum of 36" and 48" maximum below finished top of curb elevation.

  • No hand holes or pot-holing in bituminous trails unless approved by the Right-of-Way Technician.

  • All disturbed areas must be returned to their original conditions within 30 days.

  • Lawn / Blvd areas must be restored per 28-105 of the Maple Grove Code of Ordinances.

  • Must adhere to MnDOT's Standard Specifications for Construction, Section 2575 and Maple Grove's specification for grading, landscaping and traffic control.

  • Notify Right-of Way Technician when work under this permit is completed, not at year's end.

  • Flag or mark utility location as required by state statue prior to calling in locates.

  • No work shall begin this year if it cannot be properly restored this year (unless emergency).

  • Street crossings to be installed perpendicular to street whenever possible.

Invoice #300 (12/01/2016)

Charge Cost Quantity Total
Non-Taxable
added 12/01/2016 2:03 PM

Excavation permit fee per occurance

$130.00 x 1 $130.00
Grand Total
Total $130.00
Payment 12/01/2016$130.00
Due$0.00
Action: Print  

Approvals

ApprovalSignatureOptions
ApplicantAngelique Nix - 12/01/2016 2:05 PM
731f08465bcf951d0470d1ba7bebddd5
5b9ad6d92d0d72b5ead6e1bb633878d0
 
#1 Approved ByKelly Matzke - 12/02/2016 7:31 AM
ac2b3594613e885c604552b1404f0f77
dbaf5ad1db38d116a2b0778261cb45d0
 
Application has been approved. All signatures have been obtained.