Excavation Permit Utility Installation Permit No. 2020-EP292, UID # 4145
App. Status: Approved
City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369

Kelly Matzke (612-968-3615)
 

APPLICANT

Applicant:
Name:
Andy Klinnert
Company:
Arvig Enterprises Inc
Company Phone:Local Phone:
(218346 - 8247
(218346 - 5500
Email Address:
andy.klinnert@arvig.com
Mailing Address:
160 2nd St SW Perham, MN 56573
Perham MN 56573

CONTRACTOR

Contractor:
Name:
Derek Geiser
Company:
AEI Construction Arvig Enterprises Inc
Company Phone:Local Phone:
(218346 - 8247
(218346 - 5500
Email Address:
derek.geiser@arvig.com
Mailing Address:
160 2nd St SW
Perham MN 56573

PROJECT

Nature of Work:
Service Installation
Surface to be disturbed:
Boulevard
Work to start on or after: 10/26/2020
To be completed on or before: 10/31/2021
Applicant Project No.: 79348

INSTALLATION / CONSTRUCTION

Provide a detailed work description:
Construction of fiber via directional bore
Attach detailed plan sheet:
Size and kind of pipe:
(2) 1.25" Conduit with (2) 48F HDPE
Depth from surface: 36"- 48"
If other is selected, please provide additional information: NA
Length of utility construction: 17
Method of installation:
Directional Bore
Development: Existing

LOCATION

Location/Address: 12520 Elm Creek Blvd N
Mark the location of the installation
How to use:
1. Use only one option (dot, line, or polygon)
2. Made a mistake? Click on feature and press delete key.

TRAFFIC CONTROL

Will traffic control be necessary? No

Terms

ACTIVATION REQUIRED
  • Contact Kelly Matzke at (612) 968-3615 at least 24 hours prior to construction to activate permit. Failure to contact Mr. Matzke to activate permit prior to work being started shall be considered a violation of the permit and grounds for dismissing contractor from the job site.

GENERAL
  • Article IV. Public Right-of-Way Management Ordinance will be enforced for work being done in the right-of-way.

  • All excavations taking place in right-of-way must conform to Minnesota Statute Chapter 216D. Excavation Notice System.

  • All rules and regulations for locates must conform to the most current Gopher State One Handbook.

  • Excavations taking place in the Maple Grove city limits in the Hennepin County right-of-way requires permits from the City of Maple Grove and Hennepin County.

  • Flagging or painting of route required by City of Maple Grove prior to calling in Gopher State One Call ticket.

  • All properties affected by excavation and construction must be notified in writing prior to beginning work.

  • The permit issued does not in any way imply an easement on private property or grant a right to encroach on private property.

  • A City of Maple Grove Excavation Permit shall be on site at all times and available upon request by any City official.

  • Safety vests must be worn by all people occupying the right-of-way.

CONSTRUCTION
  • All underground utilities must be placed a minimum of 36” and 48” maximum below finished top of curb elevation.

  • Any placement of utilities, including but not limited to cabinets, boxes, and pedestals must conform to City Code.

  • New ground structures must be placed near existing structures at a minimum of at least five feet away from hydrants.

  • Vehicles, equipment, and materials are not allowed on any sidewalk or trail unless prior approval has been granted by a City of Maple Grove official.

  • Any changes or revisions to the Excavation Permit after approval must be resubmitted and approved before proceeding with work in the right-of-way.

  • Street crossings must be installed perpendicular to the road to avoid future potholing in street.

  • Plowing and pneuma gophering are not acceptable forms of excavation allowed in the City of Maple Grove.

  • Core drilling in street or trail requires approval prior to doing work.

  • All open trenches and holes must be backfilled before leaving work site at the end of the day.

  • All flags from locates must be removed and picked up immediately once excavation has been completed.

  • Inclement weather shall be reason for delay of the project start or suspension of the project as determined by the City of Maple Grove.

TRAFFIC CONTROL
  • All permit applications requiring traffic control shall conform to the most recent version of the Minnesota Manual on Uniform Traffic Control Devices, including the Temporary Traffic Control Zone Layouts Field Manual, and be approved by the Transporation Operations Engineer.

  • The City of Maple Grove only allows traffic control to occur during off peak hours, which is between 9:00am-3:00 pm Monday thru Friday.

  • All traffic control devices must be removed from the job site promptly upon completion of work.

  • Traffic control on weekends requires prior approval from Transportation Operations Engineer John Hagen. John can be reached via email at jhagen@maplegrovemn.gov or 763-494-6364.

RESTORATION
  • Restoration must conform to Section 28-105. Restoration of Right-of-Way.

  • Restoration Requirements on Soft Surfaces:

    1. Turf: Hydroseeding is required unless otherwise directed by Right-of-Way Technician.
    2. Soil: Six inches of topsoil is required on all boulevards that are damaged.
    3. Sprinklers: Restore to prior condition with like materials and equipment.
    4. Pet Fences: Check for continuity after repair.
    5. Landscaping: Restore to original with like materials.
  • Removal/Restoration Requirements on Hard Surfaces:

    1. Bituminous: Shall be removed and restored in a timely matter to its original or better condition.
    2. Concrete: Shall be removed and restored in a timely matter to its original or better condition.
    3. Driveways: Notify Right-of-Way Technician of any damage and address with homeowner.
  • All disturbed areas during excavation must be restored to their original condition within 30 days.

  • Damage on boulevards due to vehicles and equipment must be restored and treated the same way that excavation damage is restored.

  • Work completed in winter months must notify City with plans for restoration to take place in the spring.

  • Once restoration has been completed, contact Kelly Matzke at (612) 968-3615 or change status on permit software so an inspection can be completed in a timely manner. Failure to notify the City will result in all permits with the City of Maple Grove being put on hold until notification takes place.

ADDITIONAL INFORMATION
  • All contractors, including subcontractors, must be registered with the City of Maple Grove to do work in the right-of-way. Contractors doing work in the right-of-way that are not registered with the City will be considered in violation, and will be dismissed from the work site until registration is completed.

  • Absolutely no removal of bituminous or cement is allowed during winter working months without approval.

Invoice #3627 (10/20/2020)

Charge Cost Quantity Total
Non-Taxable
added 10/20/2020 8:55 AM

Excavation permit fee per occurance

$160.00 x 1 $160.00
added 10/20/2020 8:55 AM

In addition to excavation permit fee (per lineal foot)

$0.40 x 17 $6.80
Grand Total
Total $166.80
Payment 10/20/2020$166.80
Due$0.00

SPECIAL PROVISIONS

It is assumed that the proposed work will not impact travel lanes and/or shoulders along Elm Creek Blvd, and that staging will not impact pedestrian traffic along the existing sidewalks/trails. If the proposed work will impact either of these two items, a traffic control plan will need to be submitted and approved. Any proposed work and/or traffic control placed within the Elm Creek Blvd right-of-way will need approval by Hennepin County.

Approvals

ApprovalSignature
ApplicantAndy Klinnert - 10/30/2020 8:47 AM
4d5e4b48f1e54b64022cec6daed2f8e0
7d836817f574d2057e2ddb336a374051
#1 Right of Way Technician ApprovalKelly Matzke - 10/30/2020 8:58 AM
f15381f83a0bf87017efbf8b606d06b1
a12d867c9629ba6801b927b5eccfabc4
Application has been approved. All signatures have been obtained.

Public Notes

Text:
It is assumed that the proposed work will not impact travel lanes and/or shoulders along Elm Creek Blvd, and that staging will not impact pedestrian traffic along the existing sidewalks/trails.  If the proposed work will impact either of these two items, a traffic control plan will need to be submitted and approved.  Any proposed work and/or traffic control placed within the Elm Creek Blvd right-of-way will need approval by Hennepin County.
File(s):

    Internal Notes

    Text:
    File(s):
      Powered by