Excavation Permit Utility Installation Permit No. 2019-239, UID # 3270
App. Status: Approved
City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369

Kelly Matzke (612-968-3615)
 

APPLICANT

Applicant:
Name:
Cindy Lou Albright
Company:
Telcom Construction
Company Phone:Local Phone:
(320286 - 8369
(320286 - 8369
Email Address:
cindy.albright@telcomconstruction.com
Mailing Address:
PO Box 189
Clearwater MN 55320

PROJECT

Nature of Work:
Main Installation
Surface to be disturbed:
Boulevard
Work to start on or after: 09/10/2019
To be completed on or before: 03/10/2020
Applicant Project No.: N.592585

INSTALLATION / CONSTRUCTION

Provide a detailed work description:
Access only for splicing at HH 1422-HH15
Attach detailed plan sheet:
Size and kind of pipe:
access only
Depth from surface: 36"- 48"
Length of utility construction: 0
Method of installation:
Other
If other is selected, please provide additional information:
access only
Machine excavation: No
Development: Existing

LOCATION

Location/Address: 6820 Wedgewood Rd N / Wedgwood Commerce Centre 14th Addn
Mark the location of the installation
How to use:
1. Use only one option (dot, line, or polygon)
2. Made a mistake? Click on feature and press delete key.
Will traffic control be necessary? No
Will any excavation be taking place on Hennepin County right-of-way? No

Terms

ACTIVATION REQUIRED
  • Contact Kelly Matzke at (612) 968-3615 at least 24 hours prior to construction to activate permit. Failure to contact Mr. Matzke to activate permit prior to work being started shall be considered a violation of the permit and grounds for dismissing contractor from the job site.

GENERAL
  • Article IV. Public Right-of-Way Management Ordinance will be enforced for work being done in the right-of-way.

  • All excavations taking place in right-of-way must conform to Minnesota Statute Chapter 216D. Excavation Notice System.

  • All rules and regulations for locates must conform to the most current Gopher State One Handbook.

  • Flagging or painting of route required by City of Maple Grove prior to calling in Gopher State One Call ticket.

  • All properties affected by excavation and construction must be notified in writing prior to beginning work.

  • The permit issued does not in any way imply an easement on private property or grant a right to encroach on private property.

  • A City of Maple Grove right-of-way approved permit shall be on site at all times and available upon request by any City official.

  • Safety vests must be worn by all people occupying the right-of-way.

CONSTRUCTION
  • All underground utilities must be placed a minimum of 36” and 48” maximum below finished top of curb elevation.

  • New ground structures must be placed near existing structures at a minimum of at least five feet away from hydrants.

  • Vehicles, equipment, and materials are not allowed on any sidewalk or trail unless prior approval has been granted by a City of Maple Grove official.

  • Notify Kelly Matzke at 612-968-3615 of any changes or revisions made to right-of-way permits that have already been approved by the City of Maple Grove.

  • Street crossings must be installed perpendicular to the road to avoid future potholing in street.

  • Plowing and pneuma gophering are not acceptable forms of excavation allowed in the City of Maple Grove.

  • Core drilling in street or trail requires approval prior to doing work.

  • All open trenches and holes must be backfilled before leaving work site at the end of the day.

  • All flags from locates must be removed and picked up immediately once excavation has been completed.

  • Inclement weather shall be reason for delay of the project start or suspension of the project as determined by the City of Maple Grove.

TRAFFIC CONTROL
  • All permit applications requiring traffic control shall conform to the most recent version of the Minnesota Manual on Uniform Traffic Control Devices Minnesota Manual on Uniform Traffic Control Devices, including the Temporary Traffic Control Zone Layouts Field Manual Temporary Traffic Control Zone Layouts Field Manual, and be approved by the Transporation Operations Engineer.

  • The City of Maple Grove only allows traffic control to occur during off peak hours, which is between 9:00am-3:00 pm Monday thru Friday.

  • Traffic control on weekends requires prior approval from Transportation Operations Engineer John Hagen. John can be reached via email at jhagen@maplegrovemn.gov or 763-494-6364

RESTORATION
  • Restoration must conform to Section 28-105. Restoration of Right-of-Way.

  • Restoration Requirements on Soft Surfaces:

    1. Turf: Hydroseeding is required unless otherwise directed by Right-of-Way Technician.
    2. Soil: Six inches of topsoil is required on all boulevards that are damaged.
    3. Sprinklers: Restore to prior condition with like materials and equipment.
    4. Pet Fences: Check for continuity after repair.
    5. Landscaping: Restore to original with like materials.
  • Removal/Restoration Requirements on Hard Surfaces:

    1. Bituminous: Shall be removed and restored in a timely matter to its original or better condition.
    2. Concrete: Shall be removed and restored in a timely matter to its original or better condition.
    3. Driveways: Notify Right-of-Way Technician of any damage and address with homeowner.
  • All disturbed areas during excavation must be restored to their original condition within 30 days.

  • Damage on boulevards due to vehicles and equipment must be restored and treated the same way that excavation damage is restored.

  • Work completed in winter months must notify City with plans for restoration to take place in the spring.

  • Once restoration has been completed, contact Kelly Matzke at (612) 968-3615 or change status on permit software so an inspection can be completed in a timely manner. Failure to notify the City will result in all permits with the City of Maple Grove being put on hold until notification takes place.

ADDITIONAL INFORMATION
  • All contractors, including subcontractors, must be registered with the City of Maple Grove to do work in the right-of-way. Contractors doing work in the right-of-way that are not registered with the City will be considered in violation, and will be dismissed from the work site until registration is completed.

  • Absolutely no removal of bituminous or cement is allowed during winter working months without approval.

Invoice #2832 (08/27/2019)

Charge Cost Quantity Total
Non-Taxable
added 08/27/2019 4:36 PM

Excavation permit fee per occurance

$160.00 x 1 $160.00
Grand Total
Total $160.00
Payment 08/27/2019$160.00
Due$0.00

Approvals

ApprovalSignature
ApplicantCindy L. Albright - 08/27/2019 4:36 PM
bf501d5bc0b32ed74b8563eb25143e89
3ea2c722d6d04b494b57dc1ceb7f6949
#1 Approved ByKelly Matzke - 08/29/2019 9:03 AM
2eaadf8a477f34d54e5bf38e9cc383a5
e54a63d6783f3a4fb25ad3ceb809726f
Application has been approved. All signatures have been obtained.