Excavation Permit Utility Installation UID # 1200
App. Status: Canceled
Valid: 09/13/2017 - 12/12/2017
City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369

Kelly Matzke (612-968-3615)
 

APPLICANT

Applicant:
Name:
Zelalem Kidane
Company:
CenturyLink
Company Phone:Local Phone:
(651312 - 5358
(651312 - 5358
Email Address:
zelalem.kidane1@centurylink.com
Mailing Address:
425 Monroe Street
Anoka MN 55303
Additional email address to notify: becky.richter@centurylink.com

PROJECT

Nature of Work:
Service Installation
Surface to be disturbed:
Boulevard
Work to start on or after: 09/13/2017
To be completed on or before: 12/12/2017
Applicant Project No.: N.287345

INSTALLATION / CONSTRUCTION

Provide a detailed work description:
To place fiber cable in joint trench from existing handhole on Scherber Lane.
Attach detailed plan sheet:
Size and kind of pipe:
1.25 PVC innerduct with fiber cable
Depth from surface: 36"- 48"
Length of utility construction: 1666
Method of installation:
Joint Trench (Other)
Machine excavation: Yes
Development: New

LOCATION

Location/Address: Sundance Woods Fifth Edition
Will traffic control be necessary? No
Will any excavation be taking place on Hennepin County right-of-way? No

Terms

ACTIVATION REQUIRED
  • Contact Kelly Matzke at (612) 968-3615 at least 24 hours prior to construction to activate permit. Failure to contact Mr. Matzke to activate permit prior to work being started shall be considered a violation of the permit and grounds for dismissing contractor from the job site.

GENERAL
  • Article IV. [url=https://www.municode.com/library/mn/maple_grove/codes/code_of_ordinances?nodeId=COOR_CH28STSIOTPUPL_ARTIVPURI-WMA]Public Right-of-Way Management Ordinance[/url] will be enforced for work being done in the right-of-way.

  • All excavations taking place in right-of-way must conform to [url=https://www.revisor.mn.gov/statutes/?id=216D]Minnesota Statute Chapter 216D. Excavation Notice System[/url].

  • All rules and regulations for locates must conform to the most current [url=http://www.gopherstateonecall.org/images/GSOCHandbookOnlineVersion.compressed.pdf]Gopher State One Handbook[/url].

  • Flagging or painting of route required by City of Maple Grove prior to calling in Gopher State One Call ticket.

  • All properties affected by excavation and construction must be notified in writing prior to beginning work.

  • It is recommended that jobs that consist of more than 1000 feet in length set up meets with locators.

  • A City of Maple Grove right-of-way approved permit shall be on site at all times and available upon request by any City official.

  • Safety vests must be worn by all people occupying the right-of-way.

  • Work being done on Hennepin County right-of-way requires notification permit with City of Maple Grove and a Hennepin County right-of-way permit.

CONSTRUCTION
  • All underground utilities must be placed a minimum of 36” and 48” maximum below finished top of curb elevation.

  • Vehicles, equipment, and materials are not allowed on any sidewalk or trail unless prior approval has been granted by a City of Maple Grove official.

  • Notify Kelly Matzke at 612-968-3615 of any changes or revisions made to right-of-way permits that have already been approved by the City of Maple Grove.

  • Street crossings must be installed perpendicular to the road to avoid future potholing in street.

  • Plowing and pneuma gophering are not acceptable forms of excavation allowed in the City of Maple Grove.

  • Core drilling in street or trail requires approval prior to doing work.

  • All open trenches and holes must be backfilled before leaving work site at the end of the day.

  • All flags from locates must be removed and picked up immediately once excavation has been completed.

TRAFFIC CONTROL
  • All permit applications requiring traffic control shall conform to the most recent version of the Minnesota Manual on Uniform Traffic Control Devices [url=http://www.dot.state.mn.us/trafficeng/publ/mutcd/index.html] Minnesota Manual on Uniform Traffic Control Devices[/url], including the Temporary Traffic Control Zone Layouts Field Manual [url=https://www.dot.state.mn.us/trafficeng/publ/fieldmanual/fieldmanual.pdf] Temporary Traffic Control Zone Layouts Field Manual[/url], and be approved by the Transporation Operations Engineer.

  • The City of Maple Grove only allows traffic control to occur during off peak hours, which is between 9:00am-3:00 pm Monday thru Friday.

  • Traffic control on weekends requires prior approval from Transportation Operations Engineer John Hagen. John can be reached via email at [url=mailto:jhagen@maplegrovemn.gov]jhagen@maplegrovemn.gov[/url] or 763-494-6364

RESTORATION
  • Restoration must conform to [url=https://library.municode.com/mn/maple_grove/codes/code_of_ordinances?nodeId=COOR_CH28STSIOTPUPL_ARTIVPURI-WMA_S28-105RERI-W]Section 28-105. Restoration of Right-of-Way [/url].

  • All disturbed areas during excavation must be restored to their original condition within 30 days.

  • Damage on boulevards due to vehicles and equipment must be restored and treated the same way that excavation damage is restored.

  • Work completed in winter months must notify City with plans for restoration to take place in the spring.

  • Once restoration has been completed, contact Kelly Matzke at (612) 968-3615 or change status on permit software so an inspection can be completed in a timely manner. Failure to notify the City will result in all permits with the City of Maple Grove being put on hold until notification takes place.

ADDITIONAL INFORMATION
  • All contractors, including subcontractors, must be registered with the City of Maple Grove to do work in the right-of-way. Contractors doing work in the right-of-way that are not registered with the City will be considered in violation, and will be dismissed from the work site until registration is completed.

  • Absolutely no removal of bituminous or cement is allowed during winter working months without approval.

Invoice #1078 (08/28/2017)

Charge Cost Quantity Total
Non-Taxable
added 08/28/2017 7:31 AM

Excavation permit fee per occurance

$130.00 x 1 $130.00
added 08/28/2017 7:31 AM

In addition to excavation permit fee (per lineal foot)

$0.20 x 1,666 $333.20
Grand Total
Total $463.20
Payment 08/28/2017$463.20
Due$0.00
This Application was canceled, so you may not pay for this Invoice.

Approvals

ApprovalSignature
ApplicantBecky Richter - 08/28/2017 7:31 AM
d49856ef946eeb66e4d7f8c6f1c9b92c
a26bfcba927f1490cef55e9bad2e8bf4
#1 Right of Way Technician Approval 

Public Notes

Text:
File(s):

    Internal Notes

    Text:
    File(s):
      Powered by