Excavation Permit Utility Installation Permit No. 2017-170, UID # 1126
App. Status: Approved
Valid: 07/10/2017 - 12/31/2017
City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369

Kelly Matzke (612-968-3615)
 

APPLICANT

Applicant:
Name:
Thomas John Fakler
Company:
Xcel Energy
Company Phone:Local Phone:
(651229 - 5536
(651415 - 3876
Email Address:
thomas.j.fakler@xcelenergy.com
Mailing Address:
825 Rice Street
St. Paul MN 55117

PROJECT

Nature of Work:
Main Installation
Surface to be disturbed:
Boulevard
Work to start on or after: 07/10/2017
To be completed on or before: 12/31/2017
Applicant Project No.: 12551673

INSTALLATION / CONSTRUCTION

Provide a detailed work description:
Install 35KV 1/0 AL J Primary in a joint trench with gas, telephone, and cable TV
Feeder is ECK322 and is currently operating at 34.5KV
Install single voltage 19920 Transformers
Direct Bore primary along County Road 30 back of R/W to T24
Run new joint trench 5ft back of curb, Water-Stops/Sewer Tails extend 10ft back of curb
Run new joint trench minimum 10ft back of proposed building
Drainage and Utility Easement over all of Outlot A
Attach detailed plan sheet:
Size and kind of pipe:
35KV 1/0 AL J FULL
PRIMARY = 2,580 LF
350 AL TX SEC. = 1,240 LF
#6 AL DX SEC. = 280 LF
Depth from surface: 36"- 48"
Length of utility construction: 900
Method of installation:
Directional Bore
Machine excavation: Yes
Development: New

LOCATION

Location/Address: Cambridge Park 2nd Addition
Mark the installation/construction
location on the map:
Mark the location of the installation
How to use:
1. Use only one option (dot, line, or polygon)
2. Made a mistake? Click on feature and press delete key.
Will traffic control be necessary? No
Will any excavation be taking place on Hennepin County right-of-way? Yes

EXCAVATION LOCATION

How much work is going to be performed in right of way? All in Hennepin County

Terms

ACTIVATION REQUIRED
  • Contact Kelly Matzke at (612) 968-3615 at least 24 hours prior to construction to activate permit. Failure to contact Mr. Matzke to activate permit prior to work being started shall be considered a violation of the permit and grounds for dismissing contractor from the job site.

GENERAL
  • Article IV. [url=https://www.municode.com/library/mn/maple_grove/codes/code_of_ordinances?nodeId=COOR_CH28STSIOTPUPL_ARTIVPURI-WMA]Public Right-of-Way Management Ordinance[/url] will be enforced for work being done in the right-of-way.

  • All excavations taking place in right-of-way must conform to [url=https://www.revisor.mn.gov/statutes/?id=216D]Minnesota Statute Chapter 216D. Excavation Notice System[/url].

  • All rules and regulations for locates must conform to the most current [url=http://www.gopherstateonecall.org/images/GSOCHandbookOnlineVersion.compressed.pdf]Gopher State One Handbook[/url].

  • Flagging or painting of route required by City of Maple Grove prior to calling in Gopher State One Call ticket.

  • All properties affected by excavation and construction must be notified in writing prior to beginning work.

  • It is recommended that jobs that consist of more than 1000 feet in length set up meets with locators.

  • A City of Maple Grove right-of-way approved permit shall be on site at all times and available upon request by any City official.

  • Safety vests must be worn by all people occupying the right-of-way.

  • Work being done on Hennepin County right-of-way requires notification permit with City of Maple Grove and a Hennepin County right-of-way permit.

CONSTRUCTION
  • All underground utilities must be placed a minimum of 36” and 48” maximum below finished top of curb elevation.

  • Vehicles, equipment, and materials are not allowed on any sidewalk or trail unless prior approval has been granted by a City of Maple Grove official.

  • Notify Kelly Matzke at 612-968-3615 of any changes or revisions made to right-of-way permits that have already been approved by the City of Maple Grove.

  • Street crossings must be installed perpendicular to the road to avoid future potholing in street.

  • Plowing and pneuma gophering are not acceptable forms of excavation allowed in the City of Maple Grove.

  • Core drilling in street or trail requires approval prior to doing work.

  • All open trenches and holes must be backfilled before leaving work site at the end of the day.

  • All flags from locates must be removed and picked up immediately once excavation has been completed.

TRAFFIC CONTROL
  • All permit applications requiring traffic control shall conform to the most recent version of the Minnesota Manual on Uniform Traffic Control Devices [url=http://www.dot.state.mn.us/trafficeng/publ/mutcd/index.html] Minnesota Manual on Uniform Traffic Control Devices[/url], including the Temporary Traffic Control Zone Layouts Field Manual [url=https://www.dot.state.mn.us/trafficeng/publ/fieldmanual/fieldmanual.pdf] Temporary Traffic Control Zone Layouts Field Manual[/url], and be approved by the Transporation Operations Engineer.

  • The City of Maple Grove only allows traffic control to occur during off peak hours, which is between 9:00am-3:00 pm Monday thru Friday.

  • Traffic control on weekends requires prior approval from Transportation Operations Engineer John Hagen. John can be reached via email at [url=mailto:jhagen@maplegrovemn.gov]jhagen@maplegrovemn.gov[/url] or 763-494-6364

RESTORATION
  • Restoration must conform to [url=https://library.municode.com/mn/maple_grove/codes/code_of_ordinances?nodeId=COOR_CH28STSIOTPUPL_ARTIVPURI-WMA_S28-105RERI-W]Section 28-105. Restoration of Right-of-Way [/url].

  • All disturbed areas during excavation must be restored to their original condition within 30 days.

  • Damage on boulevards due to vehicles and equipment must be restored and treated the same way that excavation damage is restored.

  • Work completed in winter months must notify City with plans for restoration to take place in the spring.

  • Once restoration has been completed, contact Kelly Matzke at (612) 968-3615 or change status on permit software so an inspection can be completed in a timely manner. Failure to notify the City will result in all permits with the City of Maple Grove being put on hold until notification takes place.

ADDITIONAL INFORMATION
  • All contractors, including subcontractors, must be registered with the City of Maple Grove to do work in the right-of-way. Contractors doing work in the right-of-way that are not registered with the City will be considered in violation, and will be dismissed from the work site until registration is completed.

  • Absolutely no removal of bituminous or cement is allowed during winter working months without approval.

HENNEPIN COUNTY RIGHT OF WAY
  • Since all or partial work will be completed in the Hennepin County Right of Way, you are also required to submit an application to [url=https://roadpermits.co.hennepin.mn.us/]Hennepin County[/url].

Invoice #965 (06/28/2017)

Charge Cost Quantity Total
Grand Total
Total $0.00
Due$0.00

Approvals

ApprovalSignature
ApplicantThomas J. Fakler - 06/28/2017 2:42 PM
9169071b7cb8bee32006d656f356dccb
77159179029e5911d5fc5447a2927df1
#1 Approved ByKelly Matzke - 08/16/2017 10:57 AM
475ca77d51deb9f841ee42dea9349d8a
9cb415c9c3e8b915afb7febd2e8bf081
Application has been approved. All signatures have been obtained.

Public Notes

Text:
File(s):

    Internal Notes

    Text:
    File(s):