Excavation Permit Utility Installation Permit No. 2024-EP071, UID # 6798
App. Status: Work Completed
City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369

Kelly Matzke (612-968-3615)
 

APPLICANT

Applicant:
Name:
McClay Lyford
Company:
Comcast
Company Phone:Local Phone:
(651925 - 6372
(651925 - 6372
Email Address:
mcclay_lyford@comcast.com
Mailing Address:
4255 Lexington Ave N.
Suite 100
Arden Hills MN 55126

CONTRACTOR

Contractor:
Name:
Eric Witt
Company:
Universal Services, Inc
Company Phone:Local Phone:
(651764 - 1640
(651764 - 1640
Email Address:
ewitt@usi-universal.com
Mailing Address:
12151 120th St. S
Hastings MN 55033

PROJECT

Nature of Work:
Main Installation
Service Installation
Surface to be disturbed:
Boulevard
Work to start on or after: 03/11/2024
To be completed on or before: 03/11/2025
Applicant Project No.: JB0001725801

INSTALLATION / CONSTRUCTION

Provide a detailed work description:
Comcast Relocate Job # JB0001725801 - Relocating cables from aerial to underground due to Power Company removing poles: Directional boring for placement of (2) 2" HDPE conduits. Wreck-Out (remove) aerial strand and cables.from poles.
Attach detailed plan sheet:
Size and kind of pipe:
2" HDPE Conduit
Depth from surface: 36"- 48"
Length of utility construction: 60
Method of installation:
Directional Bore
Development: Existing

LOCATION

Location/Address: 9475 Jefferson Highway
Mark the location of the installation
How to use:
1. Use only one option (dot, line, or polygon)
2. Made a mistake? Click on feature and press delete key.

TRAFFIC CONTROL

Will traffic control be necessary? Yes

TRAFFIC CONTROL PLAN

Attach Traffic Control Plan:

Terms

DEFINITIONS
  • Public right-of-way. "public right-of-way" means the area on, below, or above a public roadway, highway, street, cartway, bicycle lane, and public sidewalk in which the local government unit has an interest, including other dedicated rights-of-way for travel purposes and utility easements of local government units. A public right-of-way does not include the airwaves above a public right-of-way with regard to cellular or other nonwire telecommunications or broadcast service.

    City. "City" means the City of Maple Grove, Minnesota.

    Indemnified Parties. "Indemnified Parties" means the City and its elected and appointed officials, officers, employees, contractors, and agents.

    Terms and Conditions. "Terms and Conditions" means these 2023 Terms and Conditions on Excavation Permit.

ACTIVATION REQUIRED
  • Contact Kelly Matzke at (612) 968-3615 at least 24 hours prior to construction to activate permit, provide contractor contact information, start date, and anticipated completion date. Failure to contact Mr. Matzke to activate permit prior to work being started shall be considered a violation of the permit and grounds for dismissing contractor from the job site and revocation of permit approval.

GENERAL
  • (1) City Code Art. IV. - Public Right-of-Way Management will be enforced for work being done in the public right-of-way; (2) Underground installation requirements are determined through City Code 28-124; (3) All excavations taking place in public right-of-way must conform to Minn. Stat. 216D - Excavation Notice System; (4) All rules and regulations for locates must conform to the most current Gopher State One Handbook; (5) Excavations taking place in the Maple Grove city limits in the Hennepin County public right-of-way requires permits from the City and Hennepin County; (6) All properties affected by excavation and construction must be notified in writing prior to beginning work; (7) The permit issued does not in any way imply an easement on private property or grant a right to encroach on private property; (8) A City Excavation Permit shall be on site at all times and available upon request by any City official; and (9) Safety vests must be worn by all people occupying the public right-of-way.

CONSTRUCTION
  • (1) All underground utilities must be placed a minimum of 36" and 48" maximum below finished top of curb elevation; (2) Any placement of utilities, including but not limited to cabinets, boxes, and pedestals must conform to City Code; (3) Absolutely no removal of bituminous or concrete is allowed without prior approval from the City; (4) Core drilling is not allowed in street, sidewalk, or trail without prior approval from the City. The City does not allow core drilling to take place in ped ramps; (5) Vehicles, equipment, and materials are not allowed on sidewalks, trails, or ped ramps at any time unless the contractor performing work has exhausted all other alternatives, including, but not limited to lane closures and boulevard parking. If it has been determined that all alternatives have been exhausted, permission must be obtained from City representative before proceeding to use sidewalks, trails, or ped ramps; (6) Any changes or revisions to the City Excavation Permit after approval must be resubmitted, subject to the review and approval of the City Director of Public Works or designee, before proceeding with work in the public right-of-way; (7) Street crossings must be installed perpendicular to the improved street area to avoid future potholing in improved street area; (8) Plowing and pneuma gophering are not acceptable forms of excavation allowed in the City; (9) All open trenches and holes must be backfilled before leaving work site at the end of the day; (10) Street, trails, and sidewalks must be kept clean, neat, and presentable at all times; (11) All flags from locates must be removed and picked up immediately once excavation has been completed; and (12) Inclement weather shall be reason for delay of the project start or suspension of the project as determined by the City.

TRAFFIC CONTROL
  • (1) All permit applications requiring traffic control shall conform to the most recent version of the Minnesota Manual on Uniform Traffic Control Devices, including, but not limited to, the Temporary Traffic Control Zone Layouts Field Manual, and is subject to the review and approval of the City Transportation Operations Engineer; (2) The City only allows traffic control to occur during off peak hours, which is between 9:00am-3:00 pm Monday thru Friday; (3) All traffic control devices must be removed from the job site promptly upon completion of work; and (4) Traffic control on weekends requires prior approval from City Transportation Operations Engineer John Hagen. John can be reached via email at jhagen@maplegrovemn.gov or (763) 494-6364.

RESTORATION
  • (1) Restoration must conform to City Code 28-105 - Restoration of Right-of-Way; (2) Restoration Requirements on Soft Surfaces - (a) Turf - hydroseeding or seed with erosion control blankets required unless otherwise directed by Right-of-Way Technician, (b) Soil - six inches of topsoil is required on all boulevards that are damaged, (c) Sprinklers - restore to prior condition with like materials and equipment, (d) Pet Fences - check for continuity after repair, (e) Landscaping - restore to original with like materials; (3) Removal/Restoration Requirements on Hard Surfaces - (a) Bituminous - shall be removed and restored in a timely matter to its original or better condition, (b) Concrete - shall be removed and restored in a timely matter to its original or better condition, (c) Driveways - notify City Right-of-Way Technician of any damage and address with homeowner; (4) Restoration Requirements in areas where core drills were approved - (a) Bituminous - core drills in bituminous paths are replaced at width of path (example: 8 foot wide path is replaced 8'x8' per core), (b) Concrete - core drills in sidewalks require a minimum of two panels to be replaced per core to assure base has been properly reestablished; (5) All disturbed areas during excavation must be restored to their original condition within 7 days; (6) Damage on boulevards due to vehicles and equipment must be restored and treated the same way that excavation damage is restored; (7) Work completed in winter months must notify City of Maple Grove with plans for restoration to take place in the spring; and (8) Once restoration has been completed, contact Kelly Matzke at (612) 968-3615 or change status on permit software so an inspection can be completed in a timely manner. Failure to notify the City will result in all permits with the City being put on hold until notification takes place.

ADDITIONAL INFORMATION
  • (1) All contractors, including subcontractors, must be registered with the City to do work in the public right-of-way. Contractors doing work in the public right-of-way that are not registered with the City will be considered in violation, and will be dismissed from the work site until registration is completed; and (2) Absolutely no removal of bituminous or concrete is allowed during winter months.

MISCELLANEOUS
  • (1) By reason of the grant of a public right-of-way permits, the City does not assume any liability for injuries to persons, damage to property, or loss of service claims by parties other than the permittee or the City or claims or penalties of any sort resulting from the installation, presence, maintenance, or operation of equipment by permittee or activities of permittee; (2) The permittee shall, in accordance with Minn. R. 7819.1250, defend, indemnify, and hold harmless the Indemnified Parties from all liability or claims of liability for bodily injury or death to persons, or for property damage, in which the claim: (a) alleges a negligent or otherwise wrongful act or omission of the permittee or its employee, agent, or independent contractor from the installation, presence, maintenance, or operation of equipment by permittee or activities of permittee and alleges that the Indemnified Parties are liable, without alleging any independent negligent, or otherwise wrongful, act or omission on the part of the Indemnified Parties or (b) is based on the Indemnified Parties' negligent or otherwise wrongful act or omission in issuing the permit or in failing to properly or adequately inspect or enforce compliance with a term, condition, or purpose of the permit granted to the permittee. Permittee is not required to indemnify the Indemnified Parties for losses or claims occasioned by the negligent or otherwise wrongful act or omission of the Indemnified Parties, except to the extent authorized above regarding the issuance of a permit or the inspection or enforcement of compliance with the permit or when otherwise expressly agreed by permittee; (3) permittee shall adhere to and comply with all provisions of the Terms and Conditions, City Code, and all applicable federal, state, and local rules and regulations, including, but not limited to, Minn. Stat. 237.162 and 237.163; and (4) in the event of a conflict between the Terms and Conditions and City Code, City Code shall govern.

Invoice #6301 (02/26/2024)

Charge Cost Quantity Total
Non-Taxable
added 02/26/2024 2:33 PM

Excavation permit fee per occurance

$160.00 x 1 $160.00
Grand Total
Total $160.00
Payment 02/26/2024$160.00
Due$0.00

SPECIAL PROVISIONS

It is assumed that a minimum of a 4 foot wide accessible route will be maintained at all times along the trail that runs parallel to Jefferson Highway. If this is not possible, a revised traffic control plan needs to be submitted for approval.

Approvals

ApprovalSignature
ApplicantScott T. Sandkamp - 03/26/2024 10:53 AM
cd3501a61f209fccf352aebc408d06a4
6a5c1503e91f96955138958159b50dda
#1 Right of Way Technician ApprovalKelly Matzke - 04/05/2024 11:11 AM
932b89c620dd81d1c1832f8487c76fbd
edea8193132b7118d95f8ef9e3cc8371
#2 Traffic Operations Engineer ApprovalJohn Hagen - 04/05/2024 11:11 AM
ba883fb7d86f0625bba774ed9dc3e1ef
5a48002a7b2ae5f3c56eebab23a20805
Application has been approved. All signatures have been obtained.

Public Notes

Text:
File(s):

    Internal Notes

    Text:
    File(s):
      Powered by