City of Maple Grove
Application Information
Info | Applicant | ||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
|
Excavation Permit Utility Installation Site Inspection(s) UID # 4130
Utility Installation: Permit No. 2020-EP226
App. Status: In ProgressCity of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369
Kelly Matzke (612-968-3615)
Utility Installation: Permit No. 2020-EP226
App. Status: In ProgressCity of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369
Kelly Matzke (612-968-3615)
Inspection Details
Date: | 10/12/2020 |
Inspection: | Spoke with superintendent on job and conduit has been installed. Still need to have fiber installed and restoration should be completed this week. |
File attachment/photos: |
Public Notes
Text: | |