City of Maple Grove
App. Status: Closed
Valid: 11/15/2016 - 07/31/2017City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369
Kelly Matzke (612-968-3615)
APPLICANT
Applicant: |
|
PROJECT
Nature of Work: | Main Installation |
Surface to be disturbed: | Bituminous Boulevard |
Work to start on or after: | 11/15/2016 |
To be completed on or before: | 07/31/2017 |
Applicant Project No.: | 79602902 |
INSTALLATION / CONSTRUCTION
Attach detailed plan sheet: |
|
Size and kind of pipe: | 2" plastic |
Depth from surface: | 36"- 48" |
Length of utility construction: | 1481 |
Method of installation: | Joint Trench (Other) |
Machine excavation: | Yes |
Development: | New |
LOCATION
Location/Address: | 82nd AVE N & DEERWOOD LN |
Mark the installation/construction location on the map: |
|
Mark the location of the installation How to use: 1. Use only one option (dot, line, or polygon) 2. Made a mistake? Click on feature and press delete key. |
|
Will traffic detouring be necessary? | No |
Terms
Contact the Right-of-Way Technician by phone (612-968-3615) 24 hours prior to starting work, and upon completion so a final inspection can be completed in a timely manner.
You must adhere to [url=https://www.revisor.mn.gov/statutes/?id=216D]Minnesota Statutes 2015 CHAPTER 216D. EXCAVATION NOTICE SYSTEM[/url]
Notify all affected properties in writing prior to beginning work.
All cabinets, boxes, pedestals, etc. at corners must meet the City of Maple Grove's City Code, Sec. 360818 traffic visibility at corner lots.
All large trucks or large equipment are not allowed on any boulevard sidewalk or bituminous trails unless prior approval has been granted by the Right-of-Technician.
All signing for equipment in street must conform to the current MnDOT Manual on Uniform Traffic Control Devices.
Pneuma gophering is not allowed by the City of Maple Grove in this area.
All underground utilities must be placed a minimum of 36" and 48" maximum below finished top of curb elevation.
No hand holes or pot-holing in bituminous trails unless approved by the Right-of-Way Technician.
All disturbed areas must be returned to their original conditions within 30 days.
Lawn / Blvd areas must be restored per 28-105 of the Maple Grove Code of Ordinances.
Must adhere to MnDOT's Standard Specifications for Construction, Section 2575 and Maple Grove's specification for grading, landscaping and traffic control.
Notify Right-of Way Technician when work under this permit is completed, not at year's end.
Flag or mark utility location as required by state statue prior to calling in locates.
No work shall begin this year if it cannot be properly restored this year (unless emergency).
Street crossings to be installed perpendicular to street whenever possible.
Invoice #185 (09/17/2016)
Charge | Cost | Quantity | Total |
---|---|---|---|
added 09/17/2016 11:03 AM Excavation permit fee per occurance |
$130.00 | x 1 | $130.00 |
added 09/17/2016 11:03 AM In addition to excavation permit fee (per lineal foot) |
$0.20 | x 1,481 | $296.20 |
Grand Total | |||
Total | $426.20 | ||
Payment 09/17/2016 | $426.20 | ||
Due | $0.00 |
Approvals
Approval | Signature |
---|---|
Applicant | Kimberly K. Ignatowicz - 09/17/2016 11:03 AM 50816114a55c590db1cdfa5af202fc53 745aaa39e906dda6a4111efb5ba66a0f |
#1 Approved By | Kelly Matzke - 10/12/2016 10:15 AM 3dcfe2b9c91c4fdae8e223ef309b408f 7c9aa029fc99e658c83efc4ef3d98e11 |
Public Notes
Text: | City ordinance requires joint trench in all new subdivisions. |
File(s): |
Internal Notes
Text: | Private streets....have to check plat to see easements and possibility of joint trench?? |