Excavation Permit Utility Installation Permit No. 2016-085, UID # 107
App. Status: Closed
Valid: 07/01/2016 - 07/01/2016
City of Maple Grove
Engineering Department
12800 Arbor Lakes Parkway
Maple Grove, MN 55369

Kelly Matzke (612-968-3615)
 

APPLICANT

Applicant:
Name:
Tosha Barthel
Company:
Great River Energy
Company Phone:Local Phone:
(763445 - 5986
(612812 - 6695
Email Address:
tbarthel@grenergy.com
Mailing Address:
12300 Elm Creek Blvd
Maple Grove MN 55369

PROJECT

Nature of Work:
Other
Surface to be disturbed:
Gravel
Work to start on or after: 07/01/2016
To be completed on or before: 07/01/2016
Applicant Project No.: CP494

INSTALLATION / CONSTRUCTION

Attach detailed plan sheet:
Size and kind of pipe:
n/a
Depth from surface: Other, I will describe below
If other is selected, please provide additional information: aerial OPGW wire
Length of utility construction: 770
Method of installation:
Other
If other is selected, please provide additional information:
aerial only
Machine excavation: No
Development: Existing

LOCATION

Location/Address: 73rd Avenue North
Mark the installation/construction
location on the map:
Mark the location of the installation
How to use:
1. Use only one option (dot, line, or polygon)
2. Made a mistake? Click on feature and press delete key.
Will traffic detouring be necessary? No

Terms

Requirements
  • Contact the Right-of-Way Technician by phone (612-968-3615) 24 hours prior to starting work, and upon completion so a final inspection can be completed in a timely manner.

  • You must adhere to [url=https://www.revisor.mn.gov/statutes/?id=216D]Minnesota Statutes 2015 CHAPTER 216D. EXCAVATION NOTICE SYSTEM[/url]

  • Notify all affected properties in writing prior to beginning work.

  • All cabinets, boxes, pedestals, etc. at corners must meet the City of Maple Grove's City Code, Sec. 360818 traffic visibility at corner lots.

  • All large trucks or large equipment are not allowed on any boulevard sidewalk or bituminous trails unless prior approval has been granted by the Right-of-Technician.

  • All signing for equipment in street must conform to the current MnDOT Manual on Uniform Traffic Control Devices.

  • Pneuma gophering is not allowed by the City of Maple Grove in this area.

  • All underground utilities must be placed a minimum of 36" and 48" maximum below finished top of curb elevation.

  • No hand holes or pot-holing in bituminous trails unless approved by the Right-of-Way Technician.

  • All disturbed areas must be returned to their original conditions within 30 days.

  • Lawn / Blvd areas must be restored per 28-105 of the Maple Grove Code of Ordinances.

  • Must adhere to MnDOT's Standard Specifications for Construction, Section 2575 and Maple Grove's specification for grading, landscaping and traffic control.

  • Notify Right-of Way Technician when work under this permit is completed, not at year's end.

  • Flag or mark utility location as required by state statue prior to calling in locates.

  • No work shall begin this year if it cannot be properly restored this year (unless emergency).

  • Street crossings to be installed perpendicular to street whenever possible.

Invoice #92 (07/01/2016)

Charge Cost Quantity Total
Non-Taxable
added 07/01/2016 9:38 AM

Add obstruction fee if applicable to project.

$35.00 x 1 $35.00
Grand Total
Total $35.00
Payment 07/01/2016$35.00
Due$0.00

Approvals

ApprovalSignature
ApplicantTosha Barthel - 07/01/2016 9:38 AM
8bd2d8b3da75776d2b6ac0ef869f3bcf
5ad93d9010ba394e56898431bc631525
#1 Approved ByKelly Matzke - 07/01/2016 10:58 AM
ff7cab02497139346e7f6de7778cca31
43d1ce405a92e97e13c0e45ff796f790
Application has been approved. All signatures have been obtained.

Public Notes

Text:
File(s):

    Internal Notes

    Text:
    Crane hit 115kV aerial transmission line that goes across 494 near the 494/94 split.  Gave Great Energy permission to do work before permit is approved due to emergency.
    File(s):
      Powered by